Work progress

Short programme no.14

Right-click “open image in new tab” for full image resolution

progress_no14_page-0001 progress_no14_page-0002 progress_no14_page-0003 progress_no14_page-0004 progress_no14_page-0005 progress_no14_page-0006 progress_no14_page-0007 progress_no14_page-0008 progress_no14_page-0009 progress_no14_page-0010 progress_no14_page-0011

Update: 

The water board Contractor Morrison did not complete their programme works before the Easter holiday period as promised on 1st of April.
Their works resumed on 23th April. Full details on completion of this element of works will be available following a planned meeting between LBL, TGRAM and Thames Water contractors scheduled for 30th April 2019.

On 1st of April a representative of Morrison Contractors gave a delayed finish date of the 15th of April due Thames Water having issues shutting the main to complete works. (Updates to follow)

Short programme no. 13

1) Section 3A + 3B: In relation to the Grove Park street scene project are ON HOLD due to remedial repairs to historical leaks in the water main pipeline + network rail issues relating to the rail bridge structure.

Due to the water board works, the existing temporary signals have to remain in place to accommodate their working space requests. 

On Friday the 22nd of March a representative of Morrison Contractors (Waterboard subcontractor) gave a finished programme date of the 4th of April for their remedial works.

Once the waterboard complete the last major phases of this scheme (commissioning of new traffic signals + resurfacing of carriageway) will be carried out. Information leaflets will be issued.

2) Additional works issued from LBL on phase 6B + 6C ( see below)

3) 8C on hold due to existing tree roots requiring Project Centre to redesign footpath makeup (works to be updated)

 

Right-click “open image in new tab” for full image resolution

progress_no13_update-page-001

progress_no13_update-page-002

progress_no13_update-page-003

progress_no13_update-page-004

progress_no13_update-page-005

progress_no13_update-page-006

progress_no13_update-page-007

progress_no13_update-page-008

Short programme no. 12

1) Section 3A + 3B: In relation to the Grove Park street scene project are ON HOLD due to remedial repairs to historical leaks in the water main pipeline + network rail issues relating to the rail bridge structure.

Due to the water board works, the existing temporary signals have to remain in place to accommodate their working space requests. At present TG RAM have no works end date from the water board (website update to follow). Once the waterboard complete the last major phases of this scheme (commissioning of new traffic signals + resurfacing of carriageway) will be carried out. Information leaflets will be issued.

2) Additional works issued from LBL on phase 6B + 6C ( see below)

3) 8C on hold due to existing tree roots requiring Project Centre to redesign footpath makeup (works to be updated)

 

Right-click “open image in new tab” for full image resolution

progress_no12_update-page-001

progress_no12_update-page-002

progress_no12_update-page-003

progress_no12_update-page-004

progress_no12_update-page-005

progress_no12_update-page-006

progress_no12_update-page-007

progress_no12_update-page-008

Short programme no. 11

Right-click “open image in new tab” for full image resolution

progress_no11-01 progress_no11-02 progress_no11-03 progress_no11-04 progress_no11-05 progress_no11-06 progress_no11-07 progress_no11-08 progress_no11-09 progress_no11-10 progress_no11-11 progress_no11-12

Short programme no. 10

Right-click “open image in new tab” for full image resolution

progress_no10-01 progress_no10-02 progress_no10-03 progress_no10-04 progress_no10-05 progress_no10-06 progress_no10-07 progress_no10-08 progress_no10-09 progress_no10-10 progress_no10-11 progress_no10-12

 

Right-click “open image in new tab” for full image resolution

progress_no8-01 progress_no8-02 progress_no8-03 progress_no8-04 progress_no8-05 progress_no8-06 progress_no8-07 progress_no8-08 progress_no8-09 progress_no8-10 progress_no8-11 progress_no8-12

progress_no7-01 progress_no7-02 progress_no7-03 progress_no7-04 progress_no7-05 progress_no7-06 progress_no7-07 progress_no7-08 progress_no7-09 progress_no7-10 progress_no7-11 progress_no7-12

Update on short term programme:

Right-click “open image in new tab” for full image resolution

 

Short programme no. 6

short-programme-6-1

Click here to see full post-school holiday  programme

grove-park-short-progress-report-5-1

grove-park-short-progress-report-5-2

grove-park-short-progress-report-5-3

Short programme no. 5

short-programme-5-1

grove-park-short-progress-report-4_shortened-version-1-copy

grove-park-short-progress-report-4_shortened-version-2

grove-park-short-progress-report-4_shortened-version-3-copy

grove-park-short-progress-report-4_shortened-version-4-copysp-no2-1

sp-no3-1

sp-no4-1

Update:

Click here for works program during the school holiday

page_0page_1page_2

page_3

grove-park-short-progress-report-2_shortened-version-1

grove-park-short-progress-report-2_shortened-version-2

grove-park-short-progress-report-2_shortened-version-3

grove-park-short-progress-report-2_shortened-version-4

Update: The below leaflet will be letter dropped to over 30k residences in the SE12,SE9,SE6 & BR1 postal areas from  w/c 09/07/18.

lbl_borough_wide_advance_residents_leaflet-1

 

lbl_borough_wide_advance_residents_leaflet-2Update:  Short programme from 2nd of July to 18th of July

060718gpark_bus-routes3

Update: During the build of Phase 10a to 10i  (19th of July – 31st of August) the bus stop status as follows:

060718gpark_bus-routes2

-updates will follow-